Duqm Refinery Project - EPC # 02 (Utilities & Offsites)

Description

Fabrication, installation, and testing of FRP and HDPE underground pipes | Services - Fire Water, Oily Water Sewer, and Accidental Oil Containment | Pipe Vendor - FPI | Pipe Materials - GRE and GRVE | Joint Type - Adhesive Bonding and Lamination | Hydrotest Pressure - 24 Bar 

Project details

  • LOCATION: Special Economic Zone Duqm
  • SCOPE : FRP and HDPE Under Ground Piping - 5100 Inch Dia
  • CONTRACTOR: Petrofac & Samsung Joint Venture
  • SUB-CONTRACTOR: Bahwan Engineering Company
  • CLIENT: OQ8 (JV Between OQ & KPI)
  • PROJECT DURATION: July 2020 - Sep 2020
  • TOTAL MAN HOURS: 15,000